Essential Energy, 2014–2015
Moving an electricity network's public websites to Microsoft Azure.
We migrated Essential Energy's public websites, essentialenergy.com.au, essentialwater.com.au and the .net.au site, off a proprietary hosting service and CMS. First we lifted them to Microsoft Azure, then rebuilt them on Orchard, an open-source CMS. Outage notices, a standards library and a council streetlight portal came across intact, and operating costs fell by $3,200 a month.
- Client
- Essential Energy, the NSW Government-owned electricity distributor
- Industry
- Energy & utilities
- Services
- Cloud migration, CMS modernisation, solution design, data and application migration, integration
- Platforms
- Microsoft Azure (virtual machines, load balancing, Azure SQL, File and Blob Storage), Orchard CMS on ASP.NET MVC
- Our role
- We planned and executed the entire migration: we designed it, provisioned the Azure infrastructure and platform services, migrated the data and applications, and built the integration back to on-premise systems.
The challenge
Essential Energy's public websites ran on Virtual Office, a hosting service, with AlphaCMS, a proprietary content management system. The hosting and CMS contracts expired in March 2015. That date was fixed, and it was the whole plan's constraint: whatever happened, three live websites had to be somewhere else by then.
These weren't brochure sites. For an electricity distributor, the website is where customers check for outages, where contractors and councils find technical documents, and where councils look up information about their streetlights. Several of those features had been built inside the proprietary CMS, so they couldn't simply be exported with the pages.
A proprietary platform also meant the content and the features weren't really Essential Energy's. Every change depended on one vendor, and moving away from that vendor was the hard part.
Our approach
We split the work into two phases with different goals. Phase 1 beat the deadline; phase 2 removed the lock-in.
- Phase 1: lift and shift to Azure. Run the existing sites on Azure infrastructure with as few code changes as possible, fixing only what stopped them running in the cloud.
- Phase 2: modernise onto a non-proprietary CMS. Rebuild the sites on Orchard CMS, using Azure platform services, once the contract deadline was no longer a risk.
- Inventory before moving. List every feature, not just every page, and decide for each one: keep, rebuild or retire.
- Close the gaps between old and new architecture. A site built for one server makes assumptions, such as local files and in-memory sessions, that a load-balanced cloud breaks. We found those first.
What we built
Phase 1: load-balanced virtual machines and Azure SQL
The first landing zone was deliberately familiar: Windows virtual machines behind an Azure load balancer, with the databases moved to Azure SQL. Two machines instead of one meant a failed server or a patch window no longer took the sites down. It also exposed every place the old code assumed it was alone.
Making single-server code work on many servers
Two assumptions broke straight away. Sessions held in one server's memory were lost when the load balancer sent the next request elsewhere, so we moved session state into SQL, where every server could read it. Features that wrote files to the local disk, such as uploads and generated documents, needed shared storage, so we used Azure File Services as an interim fix. Both changes were small on purpose: the goal of phase 1 was to move, not to redesign.
Phase 2: Orchard CMS on Blob Storage
With the sites safely in Azure, we rebuilt them on Orchard, an open-source CMS built on ASP.NET MVC. Media and documents moved to Azure Blob Storage, which removed the shared file-system workaround and let the web tier scale without worrying about disks. Content was mapped from AlphaCMS into Orchard content types, and old addresses were redirected to new ones so links, bookmarks and search results kept working.
Outage notices
The outage notification area was the feature that mattered most to customers. It drew on information held inside Essential Energy's network, so we built a secure exchange of data between on-premise systems and the cloud-hosted site, rather than opening internal systems to the internet. Outage information has its own story, told in our outage notification system case study.
The standards library and the council streetlight portal
The Design & Construction Standards library publishes the technical documents that contractors and designers build to, and it records views so the business can see which documents are used. The Streetlights Information Portal gives councils information about the streetlights in their areas. Both had lived inside the proprietary CMS; we rebuilt them as Orchard modules with their behaviour intact, along with a small legacy PHP game and calculator that needed a home.
Cutover
Each site went live on Azure by switching DNS after testing against the new environment, with the old host still available to fall back to.
Architecture
Two phases, one destination.
- BeforeVirtual Office hosting and the proprietary AlphaCMS
- Phase 1Load-balanced Azure VMs, Azure SQL, SQL session state
- InterimAzure File Services for features that wrote local files
- Phase 2Orchard CMS on Azure, media in Blob Storage
- IntegrationSecure on-premise to cloud data exchange for outage notices
Phase 1 beat the contract deadline; phase 2 removed the lock-in.
Results
- $3,200a month off operating costs, with a lower total cost of ownership
- 3public websites moved off proprietary hosting and CMS
- 2phases: off the expiring host first, then onto open-source Orchard CMS
Under the hood
The Azure building blocks of 2015, used for what they were good at.
- Microsoft Azure
- Azure virtual machines
- Azure load balancing
- Azure SQL
- SQL session state
- Azure File Services
- Azure Blob Storage
- Orchard CMS
- ASP.NET MVC
- DNS cutover and redirects
Why it matters now
Most organisations still have a system like this: something that works, sits on a platform they don't control, and has a contract date coming. The technology has moved on since 2015, but the shape of the problem hasn't. Moving it safely is mostly about sequencing, inventory and finding the assumptions the old system made about where it runs. That's the core of our integrations and legacy modernisation work, and the platforms we land on are the same ones we build as web and SaaS platforms.
It's also where AI now enters the picture. The secure exchange between internal systems and a public site is the same pattern we use today when an AI assistant needs internal data: a narrow, deliberate path out, never a door left open. That's how we approach self-hosted AI.
What we'd do now
- Separate the deadline from the modernisation. Get off the expiring platform first, with the smallest change that works. Redesign once nothing is forcing your hand.
- Inventory features, not pages. Pages are easy to move. The outage feed, the document tracker and the council portal are what break, and nobody lists them until they stop working.
- Prefer platform services to servers. Today we'd land straight on managed web hosting and managed databases, with infrastructure as code, so the environment can be rebuilt from a repository rather than from memory.
- Own the content model. Choose a CMS whose data you can export in a format you understand. The cheapest migration is the one the next platform doesn't need.
- Keep internal systems inside. Push the data a public site needs out to it; never let the public site reach in.
Questions
Why migrate in two phases instead of one?
The hosting contract had a fixed end date. Lifting the existing sites to Azure first removed that deadline risk; rebuilding on a new CMS then happened on a platform we controlled, without a clock running.
What is a lift-and-shift migration?
Moving an application to new infrastructure with as few code changes as possible. Here it meant running the existing sites on load-balanced Azure virtual machines with Azure SQL, and fixing only what stopped them running on more than one server.
Why Orchard CMS?
It was open source and built on ASP.NET MVC, so the content and the custom features belonged to Essential Energy rather than a vendor, and its modules could carry the outage notices, the standards library and the council streetlight portal.
How much did the migration save?
Moving the internet site to the cloud cut operating costs by $3,200 a month and lowered the total cost of ownership.
Related
The services behind this work, and more stories like it.
Services
Case studies
Essential EnergyAn electricity network on an iPad, offline. Field Portal: custom compression for the asset map, and a form designer that removed 3,000+ paper forms and workflows.
Essential EnergyTelling customers when the power is out. The outage notification system (ONO) finds the customers an outage affects and notifies them by SMS or letter.
Essential EnergySeeing the low-voltage grid. An event-driven pipeline that placed smart-meter, battery, smart-plug and telco readings on the network, with no new sensors.
Bring us the hard problem.
A 45-minute discovery call with the engineer who'll build it.